Case study:

Herne Bay Relief Sewer

Project Overview

Herne Bay currently operates a combined wastewater and stormwater system. During heavy rain events, wastewater can discharge into the harbour. This project will deliver a 2.1 metre diameter tunnel to separate the wastewater system, with an estimated 80 percent reduction in discharge during weather events. Traffix supports the project with early works input, TMP design and submission, traffic management delivery, VMS supply, and an ongoing auditing programme within a live, public facing road corridor environment.

Project Details

Client
Ghella
Location
Herne Bay, Auckland
Industry
Utilities
Timeframe
2025 to 2029

Scope of Work

  • Consultation and coordination with Auckland Transport
  • TMP design and submission
  • Traffic management delivery
  • VMS board supply
  • Ongoing auditing programme

Key Challenges

  • Herne Bay is New Zealand’s oldest suburb, with heritage-protected buildings and a high sensitivity to visual impacts
  • Tunnelling requires major excavation at intersections, including 8 metre diameter excavations that result in full road closures
  • The wider programme can involve up to 11 road closures operating at the same time
  • High-profile stakeholder engagement, with restricted access for residents over long durations
  • Works delivered within live road corridors and live lane environments, with strong public visibility

Our Approach

Given the scale of disruption and the local environment, Traffix took a different approach to planning and delivery. Using the NZGTTM risk-based approach, the team focused on providing clear, targeted advanced warnings and relevant information to road users and residents. This supported a significant reduction in signage, reducing clutter and visual impacts while still meeting safety and compliance expectations across staged delivery.

Traffix was involved from the early design stage, providing practical input that supported best-practice traffic management, reduced overall impact, and helped keep costs under control. Dedicated STMS personnel were also involved early, so the delivery team understood the project requirements fully and could maintain a consistent, high-standard site presence.

To support positive stakeholder interactions on a high-profile project, Traffix teams completed de-escalation training, helping crews manage challenging situations calmly and professionally.

Early engagement with Auckland Transport was built into the programme, including the appointment of a dedicated Corridor Access Management contact to ensure a clear understanding of the works and the impacts, with no surprises as delivery progressed. Dedicated communication lines between traffic management, the client’s stakeholder manager, and the delivery team supported forward planning and coordinated engagement with local stakeholders.

The Outcome

Traffix supported a safer and more controlled operating environment across a complex programme of closures in a sensitive area. The risk-based approach reduced unnecessary visual impact, while early coordination and consistent communication supported smoother approvals, better stakeholder outcomes, and staged delivery aligned with the programme requirements.

The team at Traffix are amazing. From the TTM workers on the ground, the STMS’ willingness to the company’s senior management enthusiasm, no challenge is too big. They work greatly with our site teams, highly regarded by project staff, contribute to problem solving and offer the services required for large projects.

Ulrick Noesgaard
Traffic and Spoil Management
Ghella

Contact Us

Working within a high profile corridor with staged closures, tight access requirements and strong public visibility? Talk to us early and we will help plan and deliver traffic management that reduces surprises, improves coordination, and keeps the programme moving across every stage.