Safe, compliant and adaptable traffic control for every worksite.
NZGTTM has moved temporary traffic management away from a prescriptive checklist and towards a risk-based approach. Instead of defaulting to a standard setup, we assess the real conditions on site and apply controls that match the level of risk.
For clients, that can mean a traffic management plan that is more practical to deliver, creates less disruption, and supports better efficiency where the road environment allows.
CoPTTM was originally intended as guidance, but over time, it was often treated like a rulebook. NZGTTM is different. Planning starts with risk, using the hierarchy of controls to eliminate or minimise it, and requires clear justification for the selected controls.
The result is a plan built around real-world site conditions, not a one-size-fits-all default.
Risk-based planning allows the traffic management approach to be right-sized to the site. Where the road environment supports it, this can reduce unnecessary device deployment, shorten setup and pack down time, and increase workable hours.
A prescriptive CoPTTM-style setup for a worksite can quickly become device-heavy, with a larger footprint, a longer setup time, and a narrower working window. A risk-based approach allows controls to be selected to match the site conditions and achieve the same safety outcome with a simpler, more targeted setup. Outcomes will vary based on the site, scope, traffic volumes, and road-controlling authority requirements.
Fewer devices and a smaller footprint can reduce disruption, shorten changeovers and increase productive time onsite.
In one particular comparison case we found that adopting the NZGTTM approach resulted in the following improvements. These greatly reduced costs and disruptions.
Before NZGTTM was adopted nationally, we were involved in early trials of the risk-based approach on a motorway adjacent lane closure. We assessed the site risks, work window and traffic environment, then developed an alternative risk-based traffic management plan.
The trial proceeded with client approval and was authorised by Auckland Transport. A post-work debrief confirmed the methodology performed as intended, demonstrating how risk-based planning can deliver practical outcomes when applied properly.